Setup MRP - Material Requirements Planning in Oracle EBS R12
Setting up Master Scheduling/Material Requirements Planning (MRP) in Oracle E-Business Suite (EBS) R12.3 involves several configuration and master data setup steps.
Here's a step-by-step guide to set up Master Scheduling/MRP in Oracle EBS R12.3:
Step 1: Define Organizations
Navigation: Inventory > Setup > Organizations > Organizations
Define the organization where you will perform Master Scheduling/MRP activities.
Step 2: Define Item Master
Navigation: Inventory > Items > Master Items
Create item master records for each item you want to include in the MRP planning.
Step 3: Set Up Item Attributes
Navigation: Inventory > Items > Organization Items
Set up item attributes such as lead time, safety stock, lot size, and planning method for each item in the organization.
Step 4: Define BOM (Bill of Materials)
Navigation: Bills of Material > Bills > Bill of Material
Create BOMs to represent the list of components required to manufacture an assembly.
Step 5: Define Routing
Navigation: Bills of Material > Routings > Routings
Define routings to specify the sequence of operations required to manufacture an assembly.
Step 6: Set Up Master Scheduling/MRP Parameters
Navigation: Master Scheduling/MRP > Setup > Planning > Parameters
Define MRP planning parameters, such as planning horizon, safety stock days, etc.
Step 7: Set Up Master Scheduling/MRP Profile Options
Navigation: System Administrator > Profile > System
Set up profile options specific to Master Scheduling/MRP.
Step 8: Set Up Planner Codes (Optional)
Navigation: Master Scheduling/MRP > Setup > Planning > Planner Codes
Define planner codes to categorize planners or planning responsibilities.
Step 9: Set Up Planning Time Fence
Navigation: Master Scheduling/MRP > Setup > Planning > Planning Time Fence
Define the planning time fence to control the horizon within which MRP will not automatically change the planned orders.
Step 10: Run Master Scheduling/MRP
Navigation: Master Scheduling/MRP > Launch > Single Plan
Run the Master Scheduling/MRP process for the organization and set of items.
Step 11: Review MRP Output
Navigation: Master Scheduling/MRP > View > Planned Orders
Review the MRP output, including planned orders, purchase requisitions, and recommended order quantities.
Step 12: Review Exception Messages (Optional)
Navigation: Master Scheduling/MRP > View > Exception Messages
Check for any exception messages generated during the MRP run and take appropriate actions.
Step 13: Convert Planned Orders to Purchase Requisitions (Optional)
Navigation: Master Scheduling/MRP > Planning > Order Recommendations
Convert planned orders to purchase requisitions or internal requisitions, if required.